PROJECTS

CLIENT: XSTRATA

Project: BM04 Concentrator upgrade

Installation of piping, structural steel, pumps and commissioning of plant on a continual shift basis with 24 men on 6 job fronts over an 8 month period

 

CLIENT: XSTRATA

Project: Zinc Concentrator

Shutdowns

Supply up to 20 personnel, supervise up to 25 job fronts scheduled for 2-6 days per shutdown

 

CLIENT: XSTRATA

Project: EHM Shutdowns

Supply up to 20 personnel for 2-7 days both day and night shift, co-ordinate rubber lining, abrasive blasting, Losugen and all crane operation

 

CLIENT: XSTRATA

Project: Combined Maintenance

Work

Supply labour and equipment to carry out maintenance works and upgrade on numerous site locations

CLIENT: CENTURY MINE

Project: Mobile Equipment Contract

Maintain and repair wear packaging for trays, buckets and ancillaries, including rebuilds over 18 months

 

CLIENT: AUSENCO

Project: Lady Annie Mine Construction

Fabrication and installation of structures, conveyors and crushing facilities over 16 weeks

 

CLIENT: COOPERCO

Project: Lady Annie Mine

Supply labour and equipment to carry out maintenance works, minor shutdowns and upgrade over 12 months

 

CLIENT: GLENCORE

Project: George Fisher Mine Crusher Expansion Project

Installation and commissioning of winder shaft and crushing plant.

Supplied up to 20 personnel supervising 15 job fronts over 4 years

 

CLIENT: XSTRATA

Project: HMP Fire rebuild

Refurbish conveyors, chutes and structures over 60 days

CLIENT: GLENCORE

Project: Asarco Baghouse fire rebuild

Supply 105 personnel per day for 3 months to refurbish conveyors, chute and structures. Included workshop fabrication and commissioning

 

CLIENT: GLENCORE

Project: Copper Smelter Rebrick

Supply 107 personnel per day for 2 months, supervising and managing up to 30 job fronts to install and repair key smelter components

 

CLIENT: GLENCORE

Project: Lady Loretta camp installation

Installation and set-up camp structures including all electrical and plumbing works

 

CLIENT: CENTURY MINE

Project: PERCent Project

Provide structures, piping and mechanical works for new ball mill circuit over 6 months

 

CLIENT: XSTRATA

Project: Zinc Project upgrade

Installation of grinding and floatation circuit including various pipe and structural fabrications over 120 days